The first step to begin a solar system installation will be your initial contact with one of our solar specialists.  You may email or call us at any time to find out if your home qualifies for solar.  It is recommended to have your electric bill available during the initial evaluation so we may accurately calculate your annual savings.  Upon review of this information we will then coordinate a date and time to perform a solar analysis of the proposed location and so that you may sign the appropriate rebate applications and proposal.  The breakdown of the overall process is as follows:

Phase 1

2 Days
Site Visit
Sign Proposal
Sign Rebate/SREC & Utility Applications
Initial Deposit Due
Applications Submitted with Fees
 
Phase 2 4-8 Weeks
Utility Application Approved (approx 1 week)
Rebate/SREC Application Approved (approx 4-8 weeks)
 
Phase 3 1 Week
Produce Construction Drawings
Structural Letter & Final Electrical Design
Site Survey (if req')
Permit Package & Fees Submitted to Township
 
Phase 4 4-6 Weeks
Building Permit Approved
Electrical Permit Approved
Second Payment Due (Equipment Costs)
Equipment Ordered and Delivered
Coordinate Installation Start Date
 
Phase 5 4-6 Weeks
Installation Completed (approx 1-2 weeks)
State Inspection Approved
Local Inspection Approved
Final Rebate & Utility Forms Submitted
Final Payment Due
 
Phase 6 1-2 Weeks
Utility Approves Installation
Utility Installs Net-Meter
Solar System is Commissioned for Operation

Note: Times vary based on rebate approvals, township approvals, equipment availability, inclement weather during installation, inspector availability, utility approvals and availability, roof reinforcement if applicable, etc.